Frant Concrete Canvas Case Study

Problem – Concrete canvas had to be installed along a stream at the bottom of railway embankment, that was 900m away from nearest road, across soft ground. Client had planned to use rail access to get all materials to site, but were unable to, due to suitable possessions to use RRV’s being very rare.

Solution – Using our BV206 & flatbed trailer, we were able to transport the mini digger & all materials to site & remove all the logged trees away from site. Then using our 6-wheel ‘Gator’, we could transport the men & tools to site each day. All work carried out during the day without any possessions required.